Purpose: To deposit a conformal layer of metal or dielectric to the surface of a sample
Location: Marcus Inorganic Cleanroom
Tools: Denton Discovery, CVC DC Sputterer, PVD RF Sputterer, Unifilm Sputterer
Supplies Needed: targets, kapton tape (if necessary), tweezers, vacuum, isopropanol, texwipe, multi-meter, test wafer/ wafer pieces, witness wafer/ wafer piece
Setup Parameters
- Schedule time well in advance
- Know the required powers for sputtering the material you want to deposit
- Check that the back of the sample is clean and the front of the sample is free of any unwanted debris
- Vent and clean the chamber
- Vacuum inside the chamber
- Wipe down the o-ring and the chamber with isopropanol and a texwipe
- Clean off the target with isopropanol and a texwipe
- Check the target thickness prior to insertion in the tool.
- Insert the target into the tool
- Test the target with a multi-meter
- After putting the target in the tool, place one prong of the multi-meter on the target and one on the shutter or side of the chamber
- Make sure the multi-meter is set to measure continuity
- If the multi-meter measures a resistance (it should measure overload), the target is shorting and not inserted correctly
- Reseat the target and try testing for a short again
- If this becomes a problem and you can’t get the target to stop shorting, please contact the staff
- Make sure that the rotostrate is turning before closing and pumping down the tool
- Run a deposition test on the tool
- Using an extra clean wafer or wafer piece with a strip of tape across it, run the tool for a 5-10 minute deposition
- Measure the deposition with a profilometer and determine the deposition rate
- Calculate how long the process step must be run for the deposition thickness desired
Number of Substrates: < 1- 6 (4” wafer size)
Process Procedures
- Allow enough time for the tool to pump down to process pressure
- This will typically take 30-60 minutes
- Make sure the tool gets down to at LEAST the 10-5 Torr scale
- Make sure the plasma starts (if the tool has a view port)
- Check the power, current, gas flows, and pressure
- Watch the plasma to make sure it does not flicker or change color during the run (If the tool has a view port)
- Take note of the parameters both set point and actual
- Remove the sample and measure it to check the thickness of the deposition
- If the deposition is not as thick as desired, calculate the deposition rate of the process. Use this to figure out how much longer the sample needs to be run
- After the process is finished, remove the target and put it in the appropriate storage location. (dry box or the table with a slot for each target)
- Clean up the tool if necessary (Vacuum and wipe with texwipe and isopropanol)
- Pump down the tool and cancel any unused time that was scheduled
- If there is a log book for the tool, fill it with all of the required information from your process.
Verification: